Successful Spray Booth Installations
Video Chapters
- 0:00 Introduction and business segments
- 4:20 Learn from past projects
- 5:47 Project flow chart
- 11:03 Spray booth installation guidelines
- 16:27 Exhaust ductwork “fail”
- 18:45 Air makeup unit guidelines
- 21:02 AMU installation “fail”
- 22:20 Powder booths and cartridge collectors
- 23:32 Exhaust filtration “fail”
- 24:44 Oven guidelines
- 26:12 Oven installation “fail”
- 27:14 Q&A
Video Transcript
Introduction
Thanks for tuning in. Today’s goal is a quick crash course in real-world scenarios that make spray booth projects successful.
If you’re new to us, our 150,000 sq. ft. facility is in Rockwall, just east of Dallas. If you’re a distributor or end user and haven’t visited yet, come see what we’re building and meet the people you work with every day.
Three business segments
Under one roof, we run three businesses that work together:
- Core catalog equipment: pre-engineered equipment, with much of the information on our website. Pre-engineering speeds up time to market. Most general industrial catalog equipment ships in about 7–10 business days. Our batch ovens show working volume and components up front to save engineering time. Whether you’re painting a model train or a locomotive, there’s catalog equipment to match. Even our pass-through powder booth, built for a conveyorized line, is pre-engineered. Customers often ask for a small change, such as a crane rail or a few more feet, and that’s part of the catalog process.
- Engineered projects: conveyorized systems and highly custom equipment, such as an offshore oil rig booth and a seven-stage washer. Projects like these take a full team, including chemical and installation teams.
- RP Filtration products: in 2017, we acquired the RP Filtration product line and brought it in-house in Rockwall. Since then, we’ve added filter specialists, new products and programs. One of those programs supports our five-year equipment warranty. Having filtration and sheet metal under one roof gives distributors and end users a more well-rounded offering.
Successful spray booth installations: learn from past projects
I’m Chris Schoch, Regional Sales Manager at RTT Finishing Solutions. I’ve been here about nine years and have seen a lot of creative solutions. Some were application-driven, and some were just someone wanting equipment in a certain spot. There’s a lot we can learn from each other, especially from past mistakes.
It’s hard to teach booth installation over a webinar. What I can do is walk through the steps that reduce risk and point out where bad surprises happen. Those surprises can ruin projects and profitability.
We’ll cover:
- Project flow, from conception to construction
- Liquid booth guidelines: facility resources, field conditions and ductwork layout
- Air makeup unit guidelines: placement, discharge orientation and environmental conditions
- Powder booth, filtration and oven guidelines
Project flow chart
Whether it’s catalog equipment or an engineered project, it starts the same way: a new lead. If you pull up to a facility and see overspray on the outside of the building, you know there’s a problem, and the customer needs a solution.
- Define the need. Determine the size, requirements and location.
- Request a quote. Our online request-for-quote form has drop-down fields for size, voltage, phase, offsets and more. It helps us design the right solution, and it shows you which questions to ask so you avoid headaches later. Once you submit the information, you’ll typically get a quote back in about a day.
- Purchase order. After revisions, the quote leads to a purchase order. We then confirm voltage, phase and fuel through another round of checks.
- Engineering and approval drawings. Our engineers add ductwork and offsets, working directly with end users and distributors so communication flows freely and the drawings are as accurate as possible. Integrate the drawings into your facility layout, whether it’s a new build or an existing building. They show the booth’s footprint, where the air makeup unit goes, and whether offsets are needed, for example to avoid a door. This is the stage for the end user and distributor to review and revise. Technically, revisions beyond a certain number incur engineering charges. In nine years, I’ve rarely seen that happen during this phase. We understand plans change, and getting it right is what matters.
- Signed drawings. Once the drawings are signed, the signed drawing becomes the contract between the manufacturer, distributor and end user. It reflects everything from the quoting phase and every revision.
- Manufacturing. Materials are ordered, steel is cut, and the equipment is built and loaded on the truck.
- Installation. Who unloads the truck? When does installation start? Is startup needed? Ideally, the distributor and end user have scoped all of this out ahead of time, for example with a Gantt chart, so everyone’s on the same page.
The call we get almost weekly goes like this: “The booth was delivered, and yesterday my customer installed an overhead crane.” Overhead cranes are the nemesis of booth ductwork and offsets. As Mike Tyson put it, everybody has a plan until they get punched in the face.
My goal today is to give you a list of questions and lessons, so you can stay nimble and avoid these headaches.
Spray booth installation guidelines
Common reasons a liquid booth install goes wrong:
- The site changed after approval. For example, the customer added a welding table, the booth moved, and now there are different obstructions overhead.
- The measurements were wrong. On a new build, someone measured to the bottom of the trusses instead of the roof deck. Now offsets are needed, which affects performance.
- Voltage and phase don’t match. You’ll hear me say this a dozen times. We quoted 230V three-phase, and the site turned out to be single-phase or 480V. There’s always a fix, but it costs money, and most budgets don’t account for it.
- Electrical codes aren’t met. If someone buys an exhaust plenum and installs it in their facility, they’ve created a spray room. Does your customer understand the difference between a spray room and a spray booth, and the ductwork, explosion-proof motor and fixture requirements that come with it?
- Floor conditions weren’t checked. I once had a customer try to put equipment in a barn. Booths and ovens don’t come with a built-in floor unless one is specified. Most install on an industrial concrete floor.
If offsets or anything else hold up the job, it gets expensive. An experienced install crew of about four, plus rental equipment, runs about $2,500 a day. There’s no worse feeling than a crew waiting on a $90 piece of ductwork. The approval drawing is where you catch offsets, dimensions and obstructions. Ideally, the end user reviews and understands the drawing before signing off.
Basic checks:
- Electrical: verify voltage, supply, phase and ground. A common voltmeter goes a long way.
- Fan rotation: this is a big one. Fans can still move some air when spinning backward, so it isn’t always obvious. Rotation stickers help, but check before you drive 300 miles to find a fan wired backward.
- Fuel: verify natural gas or propane pressure and volume. Our equipment and controls include safety interlocks that check these.
- Level floor: I’ve heard, “The concrete’s a little banged up, but I’m just painting on top of it.” Our panels are pre-punched for nut-and-bolt assembly. If the floor isn’t level, the bolt holes won’t line up, the doors won’t be square, and the booth won’t seal, so dust gets in. The fix is to resurface the concrete, shim the equipment or pour a curb for it to sit on.
- Plumb floor: even good-looking concrete may not be plumb. In a large truck booth, heavy doors will swing open on one end and closed on the other. It looks like a ghost is painting in there, and it’s a safety issue.
Exhaust ductwork “fail”
We sold a straightforward booth that wasn’t moving air. Fan rotation, voltage and phase all checked out. As soon as we pulled up, we saw the issue: offsets, elbows and transitions throughout the facility.
All of that creates static pressure. If you don’t know about it during quoting, you get poor performance and non-compliance. If we know up front, we can solve it. Even if that was the only possible duct route, we could have used a vane-axial fan instead of a standard tube-axial fan. The catch is that vane-axial fans cost substantially more, and nobody wants that surprise after the sale.
Manifolding exhaust ductwork: you’ll have a handout with the relevant NFPA 33 excerpt. Everyone wants to manifold to minimize roof penetrations and offsets. It can work for a very small booth or piece of equipment, but in most cases it doesn’t. Our rule is no manifolded exhaust ductwork. Keep it simple.
The pictures here show ductwork done well. The risk is an incorrect roof measurement during design or install. That one mistake gets repeated across every exhaust on a large tunnel booth, spray room or side downdraft booth.
Air makeup unit guidelines
AMUs seem complex, but the concept is simple. They take in fresh outside air, heat it, and supply it to the building or the booth.
The problems are clearance and placement. Shops run short on space and try to pack equipment together. The fuel type, natural gas or propane, determines the burner orifice size. One of my colleagues had to go into the field and re-drill each orifice to make a unit work. It wasn’t recommended, and everyone accepted it as a workaround, but it’s not a good way to do it.
For gas supply, confirm there’s enough pressure and volume. Is there an oven upstream or downstream on the same gas line? Can everything run at the same time without draining the facility’s resources?
Our air makeup units have advanced controls and are typically custom designed, so ductwork can exit in different locations. A vertical discharge keeps the unit close to the building. But if the unit isn’t installed promptly or the ductwork isn’t sealed, water and moisture can get in, and nobody wants to pull a burner to drain water out of it.
Placement also depends on climate. Installed in Pennsylvania in July, an intake might look fine. Come January, a 5 ft. snow drift could pack the intake and starve the unit of fresh air. As the distributor or end user, you need to think through how the equipment will work in your process year-round.
AMU installation “fail”
Here, a 1/2" solenoid valve was installed in a 2" gas line. Best practice: never reduce pipe size or duct size. We can’t stress this enough. Our technical department is available to answer questions if you’re unsure where something goes or what to do.
We also provide a startup safety checklist for the installation phase, to make sure everything happens in the right order. When every item is checked off, installation is a breeze. It also minimizes future faults, because burner and gas pressures are set correctly and diaphragms and valves aren’t damaged.
Powder booths and cartridge collectors
Here’s another solenoid valve fail, this time on powder equipment. Even though our collectors come pre-wired, programmed and with the VFD mounted, people sometimes struggle to get them running.
The most common cartridge collector issue shows up months after installation. The customer replaces the cartridges and says they’re blinding out and they’re buying final filters every couple of weeks.
Look at what was originally supplied. Our 52" cartridge collectors have just under 400 sq. ft. of filter surface area. Many lower-cost cartridges have a third to half of that surface area. That leads to blinding and higher consumable costs, and nobody wants to send a crew 300 miles to swap filters.
Exhaust filtration “fail”
Our RP Filtration filters use layered paper with a polyester backing, and it’s important to understand how that filtration works. I won’t go into detail, because that’s Trey Peavy’s territory, but we have a webinar on it.
Oven guidelines
The same basics apply to ovens: voltage, phase and gas.
Ovens are rugged, industrial equipment, but their burners use a forced-air combustion fan. If the shop is dirty or there’s a lot of powder in the air, you’ll be pushing powder through the burners. Keep the area clean, and consider pre-filtering the burner combustion air. As the distributor or end user, you can spot this before installation and make recommendations, so nobody is disappointed with performance later.
Another common call is about oven ductwork. Our oven ductwork has adjustable nozzle slots that direct airflow for uniformity. In the left picture, the slots are opened at the center where the rack sits, which allows good airflow and better heat transfer. In the right picture, they’re mostly closed. The higher velocity coming out can knock powder off the parts. We have another webinar on heating and curing.
Our oven controls are among the best in the industry. If there’s an issue during startup, the smart control panel shows exactly what to check, such as gas pressure. With Smart Connect, you can monitor the oven from a mobile device. If you’re stuck, connect it to your local area network, and our technicians can monitor it remotely and walk you through getting it running.
Oven installation “fail”
It’s hard to fail when you’re making a pizza, but the secret sauce shouldn’t be welding slag and grinding debris. We make ovens, but we don’t recommend them for food prep.
That’s the quick tour of what to look for during installation.
Q&A
How high does the exhaust stack need to be above the building? A good rule of thumb is 6 ft. above the highest point of the building. Your local authority may require more. For example, Texas requires 1.5 times the floor-to-peak height. Always check with your local jurisdiction.
Who should approval drawings be returned to? Return them to whoever sent them. Our engineering managers are good points of contact, and there’s a dedicated email account for approvals.
Where can we get the apps you mentioned? There are links on our website that walk you through it.
Who is supposed to sign the approval drawing? We recommend the end user review and sign it, so they understand what they’re getting. On larger projects or ones involving a general contractor, some distributors sign. Typically, an end user principal or distributor principal should sign.
Does RTT Finishing Solutions offer startup service? Yes. Our service technicians provide startup, and we always recommend it for air makeup units and ovens.
Closing
The who-to-call list is on our website and in your handout. It shows each regional sales manager’s territory and contact information. If you can’t find what you need on the website, email [RTT marketing email].
All webinars are recorded and posted on our YouTube channel, along with other helpful videos. Subscribe to get notified when we upload a new one.
Thanks for joining us.
Additional Resources
Spray Booth Recipe Setup
Presented by Bryan Willis
Spray Booth Sizing and Selection
Presented by John Owed
Proper Use and Measurement of a Manometer
Presented by Cayce Carr and Trey Peavy
Spray Booth Inspection for Compliance
Presented by John Owed
Monitor Part Temperature with Smartbatch
Presented by Bryan Willis